Alerts & Updates 7th Feb 2022
SUPREME COURT: ONCE STAMP DUTY HAS BEEN PAID, THE ISSUE OF WHETHER THE STAMP DUTY PAID WAS INSUFFICIENT OR APPROPRIATE IS A QUESTION TO BE ANSWERED AT A LATER STAGE AND NOT UNDER SECTION 11(6) OF THE ARBITRATION AND CONCILIATION ACT, 1996
Intercontinental Hotels Group (India) Private Limited & Anr. v. Waterline Hotels Private Limited[1]
Reiterated the view in Vidya Drolia that ‘When in doubt, do refer’
The Supreme Court should ensure that arbitrations are carried on unless there is ‘deadwood’
The warranty provided by the Respondent in the HMA give rise to deeper issues which can be resolved at a later stage. Therefore, the issue of insufficient stamping is not ‘deadwood’.
The Supreme Court did not delve into the adequacy of the stamp duty paid.
In view of the above, the Supreme Court referred the matter to arbitration and appointed a sole arbitrator to adjudicate the issues.
Scope of intervention under Section 11(6) of the Act
The Supreme Court held that the question regarding the insufficiency of the stamp duty did not have to be considered under section 11(6). The fact that stamp duty was paid, irrespective of whether the duty was insufficient or inadequate, weighed in on the court. Therefore, once stamp duty is paid on the contract, irrespective of whether the stamp duty is proper or improper, the same shall not be an issue for consideration under section 11(6) of the Act.
Different approach from N. N. Global Mercantile
In N.N. Global Mercantile, the Supreme Court held that the phrase “duly stamped” “implies that the instrument must be stamped with the requisite amount of duty determined in accordance with the Schedule to the Act[7]. If it is found that the instrument is not stamped, or inadequately stamped, it is mandated by law to impound the instrument, and deal with it in accordance with the provisions of the Stamp Act.”[8] Then, the Supreme Court observed three scenarios under which the authority could exercise the power of impounding the instrument albeit under the Maharashtra Stamp Act. One of the scenarios being – the High Court, or the Supreme Court, as the case may be, while exercising jurisdiction under Section 11, would “impound the substantive contract which is either unstamped or inadequately stamped, and direct the parties to cure the defect before the arbitrator/tribunal can adjudicate upon the contract.” [9]
Taking a different path from this view, in the present case, the Supreme Court did not examine the nature of the contract and consequently, did not consider whether the HMA was duly stamped. Further, in exercise of its jurisdiction under section 11, the apex court did not impound the substantive contract which was purportedly inadequately stamped nor did it pass any directions to verify the assessment of stamp duty. The payment of stamp duty was sufficient to satisfy the Supreme Court for the purpose of section 11(6) of the Act, irrespective of whether the stamp duty was a proper/ appropriate assessment.
The apex court acknowledged that issues of substantive rights and obligations under the HMA would require adjudication at a later stage. However, it did not clarify whether the adjudication of rights and obligations of the main contract could proceed before complying with the mandatory provisions of the relevant stamp act. On the other hand, in N.N. Global Mercantile, the Supreme Court held that “there is no legal impediment to the enforceability of the arbitration agreement, pending payment of stamp duty on the substantive contract. The adjudication of the rights and obligations under the work order or the substantive commercial contract would, however, not proceed before complying with the mandatory provisions of the Stamp Act.” [10]
The Supreme Court, in the present judgement, has observed that it is only where a document is completely unstamped that courts might have an occasion to examine the concerns raised in N.N. Global Mercantile and that the present case was not one such scenario, since the Petitioners had paid an amount towards stamp duty. The Supreme Court therefore distinguishes the applicability of N.N. Global Mercantile by seemingly drawing a distinction between complete non-payment of stamp duty and part payment of stamp duty (even if insufficient). However, the consequences envisaged in N.N. Global Mercantile are the same irrespective of whether there was complete non-payment of stamp duty or inadequate payment of stamp duty i.e. as mentioned above, the findings were with respect to an instrument/ contract that is unstamped “or inadequately stamped”. Hence, N.N Global Mercantile did not contemplate impounding of instruments solely in cases where there is a question of complete non-stamping.
Further, although in the present judgement the Supreme Court declined to examine the nature of the substantive contract to determine the adequacy of the duty paid, it would be worthwhile to note the Supreme Court’s observations in Black Pearl Hotels[11]. In Black Pearl Hotels the nature of the substantive agreement containing an arbitration clause was disputed. The apex court in that matter held that the determination of the nature of an instrument is a judicial function and ought to be determined by the court at the stage of appointment of an arbitrator under section 11 of the Act. There was therefore, a precedent that allowed courts to pass a ruling on the nature of a document in proceedings under section 11 of the Act, that was available to this Court.
The way forward in similar matters where allegations of inadequate payment of stamp duty are levelled in proceedings under Section 11 of the Act is likely to change. In the present judgement, the Supreme Court has held that the question of adequacy of stamp duty is not be delved into at the stage of proceedings under section 11 and consequently left it to be determined at a later stage without passing any directions as to the impoundment of the underlying contract. In doing so, has the Supreme Court opened doors for applicants in pending applications under section 11 (6) of the Act? In similar situations where the arbitration agreement is in a contract, applicants may seek constitution of the tribunal once payment of any amount of stamp duty is made (irrespective of whether the stamp duty is proper/adequate).
The present judgement has been delivered by a bench that is equal in strength to N.N. Global Mercantile and Vidya Drolia. Therefore, the larger bench constituted pursuant to the reference made in N.N. Global Mercantile ought to clarify the different views adopted in these three judgements and the road ahead.
We hope you have found this information useful. For any queries/clarifications please write to us at insights@elp-in.com or write to our authors:
Ria Dalwani, Principal Associate – Email – riadalwani@elp-in.com
[1] Judgement dated 25 January 2022 in Arbitration Petition (Civil) No. 12 of 2019
[2] Garware Wall Ropes v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209
[3] Vidya Drolia and Others v. Durga Trading Corporation, 2020 SCC OnLine SC 1018.
[4] Garware Wall Ropes v. Coastal Marine Constructions & Engineering Limited (2019) 9 SCC 209
[5] N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13;
[6] Vidya Drolia and Others v. Durga Trading Corporation, 2020 SCC OnLine SC 1018;Vidya Drolia (at paragraph 92) had affirmed paragraphs 22 and 29 of Garware Wall Ropes, which in turn had followed the observations made in SMS Tea Estates. However, in NN Global Mercantile, the Supreme Court overruled SMS Tea Estates. The correctness of the said paragraph in Vidya Drolia was therefore doubted in NN Mercantile.
[7] Black Pearl Hotels (P) Ltd. v. Planet M. Retail Ltd., (2017) 4 SCC 498.
[8] N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 10.5]
[9] N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 36.2]
[10] N.N. Global Mercantile Pvt. Ltd. v. Indo Unique Flame Ltd and Ors., 2021 SCC OnLine SC 13 [Para 26]
[11] Black Pearl Hotels (P) Ltd. v. Planet M. Retail Ltd., (2017) 4 SCC 498.
As per the rules of the Bar Council of India, lawyers and law firms are not permitted to solicit work or advertise. By clicking on the "I Agree" button, you acknowledge and confirm that you are seeking information relating to Economic Laws Practice (ELP) of your own accord and there has been no advertisement, personal communication, solicitation, invitation or any other inducement of any sort whatsoever by or on behalf of ELP or any of its members to solicit any work through this website.